Upgrading the KCl Flotation Plant from 0.75 to 1.0 Million Tonnes per Year

NTi provided project management for the upgrade of the KCl flotation plant at the ICL Iberia facility in Súria, Catalonia, which increased the plant's capacity from 0.75 to 1.0 million tonnes per year. The project covered the installation and commissioning of new equipment, including high frequency screeners, vertical flotation cells, a gas-fired dryer and the associated handling facilities. The upgrade applies new technology to simplify and optimise the ore handling process, producing a coarser and better quality product while consuming less energy and reducing maintenance costs.

Project facts

Client
ICL Iberia
Location
ICL plant, Súria, Catalonia, Spain
Start
2021
Status
Under operations
Investment
€26M
NTi scope
Project management, installation and commissioning

Main scope

  • Two high frequency screeners (HFS).
  • Two vertical flotation cells (VFC, Jameson cells).
  • Gas burner for the dryer, with a drying capacity of 170 t/h.
  • Handling facilities, including slurry pipes, conveyors, chain redlers and a bucket elevator.
  • Nominal ore processing rate of 575 t/h.