A 100 m Viaduct Separating Truck and Train Traffic at the ICL Súria Site
NTi provided project and construction management for a new viaduct at the ICL Súria site, in the salt and potash mines of Súria, Catalonia. The viaduct removes the same-level crossing between trucks and trains. The structure is 100 m long and 7 m wide, with precast concrete piles as foundations, precast concrete columns and precast pre-stressed concrete beams for the deck. The viaduct was built in 2016 and 2017 for ICL Iberia and is currently in service.
Project facts
- Client
- ICL Iberia (Iberpotash SA)
- Location
- Salt and potash mines of Súria, Catalonia, Spain
- Construction
- 2016 / 2017
- Status
- In service
- Investment
- €1.2M
- NTi scope
- Project management and construction management
Our role
NTi provided project management and construction management for the viaduct, from project development through to its construction.
Main characteristics
- Length: 100 m.
- Width: 7 m.
- Foundations: precast concrete piles.
- Columns: precast concrete.
- Deck: precast pre-stressed concrete beams.